Whitewater group logo
Case Study

Helsinki Hyperscale Data Centre – Modular Water Infrastructure

Factory-Integrated Modular Water Infrastructure for Hyperscale Data Centres
Whitewater Group is delivering modular water infrastructure for hyperscale data centres in the Helsinki region, using off-site manufacturing to improve programme certainty, quality and commissioning readiness.
The Challenge

For this programme, the challenge was to deliver complete water infrastructure across multiple developments while reducing dependency on traditional site-sequential construction. Engineering, procurement and manufacture needed to progress alongside site works, without compromising technical standards or design intent.

Early coordination was critical. Mechanical, electrical, controls and pipework interfaces needed to be resolved before manufacture, reducing the risk of clashes, late-stage changes and additional work on site.

Whitewater Group’s response was to engineer the water infrastructure around off-site manufacture from the outset - moving almost the entire modular build into a controlled factory environment and creating a repeatable approach across the programme.

At a Glance

Location
Helsinki Region, Finland
Sector
Hyperscale Data Centres
CAPACITY
60MW
DELIVERY
Off-Site Manufacturing (OSM)
MODULAR SCOPE
5-module Water Treatment Building + 3-module Sprinkler Pump House
PROGRAMME REDUCTION
35%
FOOTPRINT REDUCTION
20-30%
OSM Completion
~100%

Factory Built. Site Ready.

The water infrastructure was engineered from the outset around off-site manufacture rather than adapted for modular construction later in the programme.

For the 60 MW project, the solution includes a five-module Water Treatment Building and three-module Sprinkler Pump House, together with process water tanks, underground storage, filtration and disinfection systems and an admin water treatment system.

The modular buildings were manufactured at Whitewater Group’s facility in Ballyhale, Ireland, with additional elements manufactured in Tomelloso, Spain.

Mechanical, electrical, controls and pipework installation progressed as far as practicable within the factory, with QA/QC and commissioning advanced to red-tag stage for most components before delivery.

This allowed factory production and site construction to progress concurrently, with completed modules transported to Finland when the receiving site was ready. 

Engineering More into Less Space

Digital coordination was central to the modularisation process.

Revit-based multidisciplinary coordination was used to resolve mechanical, electrical, controls and pipework interfaces before manufacture. This allowed the overall arrangement of the Water Treatment Building to be optimised around the modular delivery strategy.

The result was an approximately 20–30% reduction in the required plantroom footprint, while maintaining system functionality and the original design intent.

Resolving interfaces earlier also reduced the potential for clashes and late-stage coordination on site, moving more engineering decisions into the controlled design and manufacturing stages of the project.

Video

Built in Ireland.
Delivered to Finland.

The modular water treatment buildings were assembled and integrated at Whitewater Group’s off-site manufacturing facility in Ireland, with mechanical, electrical, controls and pipework installation completed as far as practicable before leaving the factory.

152 Days Removed from the Programme

An equivalent traditional stick-build programme was assessed at 436 days. Using Whitewater Group's off-site manufacturing methodology, the comparable programme was reduced to 284 days.

That represents a saving of 152 days - or 35% overall.

Electrical installation was 51% faster, Yellow Tag activity 58% faster and Green Tag activity 28% faster.

The improvement comes from changing the construction sequence. Procurement, fabrication and system build-out can progress while civil and structural works continue on site, rather than waiting for each stage to finish before the next begins.

Related Case Studies

Start the Conversation

Speak to an expert today

The earlier we understand the project, the more value we can add.

Talk to Whitewater Group at concept or design stage to help define the right water and cooling strategy, identify opportunities for standardisation and off-site assembly, and reduce risk before construction begins.
Woman in a white hard hat inspecting an item on the wall
Copyright © 2026. All rights reserved.
Designed by TOTEM